Expert Preparation & Application
Step 1:
Preparation
Preparation includes shot blasting and/or diamond grinding. Dust is minimized by having all grinders hooked up to vacuum systems..
Step 2:
Concrete Reconstruction
Menders and fillers are used to fix pits and cracks before the process begins.
Step 3:
Basecoat
100% solids, self-priming pure polyurea basecoat is mixed and applied.
Step 4:
Broadcasting the Chip
Immediately after the basecoat application, the chip is generously broadcast by hand, providing both color and texture to the door.
Step 5:
Scraping
the Chip
Once the basecoat is fully cured the floor is scraped and vacuumed to remove any loose or vertical standing flakes.
Step 6:
Clear Coat
The final step is to roll out the UV stable polyaspartic clear coat.